- The NYS Bar Exam is scheduled for 7/29 and 7/30. No construction work will take place on these days
- Asbestos abatement on the 5th floor is complete. Will begin abatement on the 7th floor the first week in July
- Replacement of fireproofing on the 5th floor will begin next Monday (July 7) or Tuesday (July
- Removal of the 5th floor roof has taken place. Workers are now in the process of replacing foam and concrete in this area
- Abatement of first floor classrooms has begun
- The water shut down originally scheduled for today (July 2) has been pushed back to next Tuesday (July
at 5:00 PM until Wednesday (July 9) at 6:00 AM
Update from 7/2 meeting
July 2, 2008 by mirashby